Water System Improvements
The last phase of improvements includes the construction of a new water
transmission and distribution system to connect the Bailey Ranch elevated
water storage tank to the City of Tulsa Master meter. Detailed work is
as follows:
- Transmission line (30-inch) between E. 106th Street North and N. Sheridan
Drive and the new Bailey Ranch elevated storage tank;
- Transmission line (24-inch) between the storage tank and E. 99th Street
North and N. Garnett Road;
- A booster pump station to be located in the base of the Bailey Ranch
storage tank;
- A master meter vault at E. 106th Street North and N. Sheridan Drive
and necessary interconnections to the existing service system.
Construction began in February 2006 and will be completed by June 2007.